Information on this page is drawn from "Sheetmetal Worker: Installation of large pipe overhead on roof" published by intel![]()
NOTE: Request for permission pending.
Task
Crew must install large pipe into overhead rack on the roof of a building.
Exposure
Installation of the pipe to an overhead rack required the crew to work from man lifts and ladders, forced into awkward posture and using forceful exertion.
Intervention Process
They reviewed the process, identifying areas where exposure to musculoskeletal risk factors existed and brain-stormed solutions. By installing the pipe cradles onto the rack, they were then able to bring all of the pipe into position using a crane and eliminating the need to physically handle it.
Materials
Materials did not change. Only the process for installation changed.
PDF Downloads
Sheetmetal Worker: Installation of large pipe overhead on roof![]()